Form-Scaff Profie pages
 

 
 
 
 
 
 
 
 
 
 

-_2010 Soccer Stadiums forge ahead

 
Soccer City Stadium - JHB

 
 
Contractor:

Completion Date:

Capacity:
Grinaker - LTA

Nov 2009

95 000
 
Formwork

Chosen by Grinaker-LTA as the sole Formwork supplier to
this prestigious project, Form-Scaff’s design office were
challenged to come up with innovative ways to form the
many different structures of this stadium.

570 Multi-Form Tables (6 000m²) were delivered to site
consisting of Form-Scaff’s highly acclaimed steel-on-steel
Multi-Form main – and secondary beams.

Supported on BS Props and Alu-Up Props, the table-forms
were used to cast most of the horizontal slabs of the new
stadium. Form-Scaff also supplied the special formwork
used for all the raking beams. Some of the raking beams
had to be extended, others were constructed new. Vertical
Formwork for the liftshafts and walls were done in Multi-Form.
2 500m² of Tim-Deck was also supplied to site for use on
other small flatslab areas.



General Information

Soccer City promises to be one of the greatest achievements in
stadium design and construction in FIFA history, once the renovation
to the previous FNB stadium has been completed. The FNB stadium, which was built by Grinaker in the 1980’s has largely been demolished and rebuilt to enlarge the stadium to 95 000 seats, as well as to meet
the strict standards demanded by FIFA.

The renovation will make Soccer City the largest stadium ever built for a World Cup tournament and will be the largest stadium on the African Continent.

The uniquely African stadium is designed to resemble a cooking pot with a ‘ring of fire’.
   
 


   
Click on image to enlarge.
 
 
Moses Mabhida Stadium - Durban

 
Contractor:

Completion Date:

Capacity:
Group 5 / WBHO / Pandev JV

May 2009

75 000
 

Formwork

Almost 800 tonne of supportwork and decking has been
supplied to this stadium by Form-Scaff's Durban branch.

Kwik-Stage with Form-Scaff's steel-on-steel Multi-Form
system has been chosen by Group 5 as the preferred
formwork system to complete the more than 95 000m²
of slabs on this prestigious project.

General Information

The stadium features some interesting engineering challenges:

Arch
A 350m long free span arch will hold up the roof of the stadium, the top of the arch will rise to 106m above the pitch. The arch will consist of a 5 x 5m steel hollow box and will weigh 2 600 tonne when complete. A cable car will carry visitors up the middle of the arch, to a viewing platform on the north side. The south side will have a 550-step adventure walk.


Roof
The stadium roof will consist of a 46 000m², Teflon-coated, glass- fibre membrane attached to the arch by 17 000m of 95mm diameter steel cables.

   
 

   
Click on image to enlarge.
 
 
Green Point Stadium - Cape Town

 
Contractor:

Completion Date:

Capacity:
WBHO / Murray & Roberts JV

Nov 2009

65 000
     
 
Formwork
General Information
 

Form-Sure has been awarded the contract to supply and erect
one half of all the horizontal formwork on the new Green Point
Stadium.

Tim-Deck supported on Alu-Up Props were chosen as the
preferred system to complete the more than 50 000m² of slabs
before the end of the year.

The stadium will contain 65 000 seats for the World Cup.
55 000 Seats will remain permanent and 15 000 modular seats
will be re-used in the deconstruction of the existing Green
Point Stadium and other social investment opportunities, leaving
opportunities for corporate suites to be retrofitted.

The stadium architecture focuses on the exterior appearance
as well as on the user's experience once inside the stadium
bowl.

The roof Is located above the highest level of seats, and contains
an accessible roof including the " Ring of Fire" lighting and
media zone, with catwalk access into and through the roof
structure.
   
 

   
Click on image to enlarge.
 
 
Peter Mokaba Stadium - Polokwane

 
Contractor:

Completion Date:

Capacity:
WBHO

Nov 2009

45 000
     
 
Formwork
General Information
 

Good concrete finishes on all Vertical formwork for this
project, was achieved by using Form-Scaff's Tifa and Tifa-
Lite systems.

WBHO used steel-on-steel Multi-Form on top of their own
Kwik-Stage support for most of the slabs around the stadium.
Form-Scaff's Kwik-Strip Multi-Form Drophead was very
successfully used on this project. It allows the Multi-Form
system to be stripped after a couple of days providing
improved cycle times.

The roof over the existing west stand of the Peter Mokaba Stadium
will be removed and replaced by a roof that covers the entire
western stand of the new Stadium. An additional 20 rows of seating
will be built around the entire stadium to increase capacity to
45,000.

In addition to the structural work, the Peter Mokaba Stadium will
be provided with first rate equipment, including an electronic
scoreboard in the northern stand, new floodlights, sound system
and a fire detection and protection system.
   
 

   
Click on image to enlarge.
 
 
Nelson Mandela Bay Stadium - Port Elizabeth

 
Contractor:

Completion Date:

Capacity:
Grinaker-LTA / Interbeton JV

Dec 2008

49 500
     
 
Formwork
General Information
 

Form-Scaff was called in by Grinaker-LTA and Interbeton to
assist with the slab formwork on the Port Elizabeth Stadium.
Multi-Form supported on Kwik-Stage was brought in to
replace the "Aluminium Decking" system used from another
formwork supplier.

6 000m² of Form-Scaff's steel-on-steel Multi-Form has been
delivered by our local branch in P.E.

The proposed stadium for Port Elizabeth will be an entirely new
construction. The current stadium has been deemed unsuitable for
upgrade and so a new football stadium is envisaged, which will be
incorporated within a multi-purpose facility specifically designed
to serve the community.

The Nelson Mandela Bay Stadium will be a high-tech, modern venue
and will meet every requirement needed to provide a world class
venue for the first and second round matches of the 2010
World Cup.
   
 

   
Click on image to enlarge.
 
Form-Scaff Profie pages